Coomera Connector (Stage 1)
The Stage 1 section of the Coomera Connector between Coomera and Nerang has been identified as the priority section to be built first.
ConstructionThe Stage 1 section of the Coomera Connector between Coomera and Nerang has been identified as the priority section to be built first.
ConstructionWork is being undertaken on the Pacific Motorway, Eight Mile Plains to Daisy Hill Upgrade, to improve 8kms of the Pacific Motorway (M1) between the Gateway Motorway and Watland Street.
ConstructionThe $1.5 billion Pacific Motorway Varsity Lakes to Tugun (VL2T) project is being delivered to upgrade 10km of the M1 and is being constructing in packages to ensure faster delivery and best value for money.
ConstructionThe Pacific Motorway M1 is one of Australia’s busiest highways and is a national freight route.
We want you to get where you're going more reliably, so you can spend more time doing the things you love.
The upgrade and widening of the Pacific Motorway M1 is being delivered in strategic priority stages as funding becomes available, based on traffic volumes and best value for money.
Project | Status |
Coomera interchange | Completed |
Coomera Connector Stage 1 | Construction |
Coomera Connector Future Stages | Planning |
Daisy Hill to Logan Motorway | Planning |
Eight Mile Plains to Daisy Hill | Construction |
Logan Motorway to Palm Beach |
Completed |
Loganholme to Pimpama |
Planning |
M1/M3 Gateway Merge | Completed |
Mudgeeraba to Robina |
Completed |
Mudgeeraba to Varsity Lakes | Completed |
Ormeau interchange (Exit 45) southbound off-ramp | Completed |
Ormeau interchange (North) | Planning |
Pimpama interchange (Exit 49) | Construction |
Varsity Lakes to Tugun (Exit 85 to 95) |
Construction |
Worongary to Mudgeeraba |
Completed |
Yatala South Interchange (Exit 41) | Completed |
Main Street overpass safety improvements |
Planning |
Logan Motorway to Nerang |
Planning |
Pavement widening on the Barwon Highway has been completed to improve road safety, reduce ongoing maintenance demand and provide a better driving experience for road users in the area.
This project will provide Intelligent Transport System infrastructure at various locations along the Bruce Highway between Pine River and Cairns.
Planning is underway for the future stages of the Coomera Connector – the remaining 29km between Loganholme and Coomera.
The Stage 1 section of the Coomera Connector between Coomera and Nerang has been identified as the priority section to be built first.
Coomera Connector (Stage 1) is around 16km long and will be delivered in 3 construction packages. Stage 1 Central, which is currently in the design phase, is the 8km section from Helensvale Road to Smith Street Motorway.
Coomera Connector (Stage 1) is around 16km and will be delivered in 3 construction packages. Stage 1 North, which is currently under construction, is the 4km section from Shipper Drive to Helensvale Road.
Design phase is underway for the Coomera Connector Stage 1 South package from Smith Street Motorway to Nerang-Broadbeach Road.
A major intersection upgrade to improve safety at the Cunningham and New England highways intersection is complete.
The project involves investigating safety improvements to provide a better driving experience for all road users and reduce the risk of fatal and serious injury crashes.
This project involves investigating safety improvements to provide a better driving experience for all road users and reduce the risk of fatal and serious injury crashes.
The department is improving the flood immunity and resilience of the state-controlled road network at 27 priority sites.
Traffic flow and safety are being improved on Gatton-Helidon Road.
This planning project aims to identify a new permanent alignment for Gatton–Clifton Road to bypass a 400m section that is affected and at-risk from a large and slow-moving landslip at Mount Whitestone.
A new bridge at Wyaga Creek crossing on the Gore Highway will improve flood immunity, safety and efficiency on one of Queensland's most important transport links.
This project has trialled sustainable pavement systems and products to rehabilitate deteriorating sections of the Gore Highway.
Rocky Creek Bridge was replaced to improve safety, traffic flow, flood immunity and efficiency.
Construction is complete to improve safety on Ruthven Street in Toowoomba's south.
This planning project involved investigating ways to improve safety and efficiency on the New England Highway between Hodgson Creek and the southern side of Cambooya Connection Road.
The planning projects investigated future infrastructure to improve safety and efficiency on the New England Highway, south of Toowoomba.
The department has delivered pavement widening and resurfacing works to improve safety and freight efficiency on the New England Highway between Stanthorpe and Ballandean.
The department has a planning project underway to investigate safety improvements at Back Creek on the New England Highway south of Cooyar.
The department is working with the Department of Defence to upgrade the entrance to the Borneo Barracks from the New England Highway at Cabarlah.
The bikeway project will connect Highfields to Toowoomba, providing a safer and more accessible active transport option.
The upgrade of the New England Highway between Cooyar and Bum Bum Creek has been completed, delivering critical safety and efficiency improvements south of Yarraman.
Planning is underway to improve safety, efficiency and reliability of Oakey-Pittsworth Road.
Planning is underway for the Pacific Motorway (M1) – Daisy Hill to Logan Motorway upgrade. This section of the M1 cannot accommodate current traffic volumes and, as a result, experiences frequent and prolonged periods of congestion and poor travel time reliability.
Planning and construction is underway for short and long-term upgrades of various interchanges on the Pacific Motorway (M1)
We have delivered an upgrade of the M1 between Mudgeeraba and Varsity Lakes to reduce travel time and congestion, improve safety, and increase traffic flow. Interchange enhancements have improved access on and off the motorway.
The $1.5 billion Pacific Motorway Varsity Lakes to Tugun (VL2T) project is being delivered to upgrade 10km of the M1 and is being constructing in packages to ensure faster delivery and best value for money.
Construction to upgrade the M1/M3 Gateway merge to improve safety and reduce peak hour congestion was completed in May 2020.
Work is being undertaken on the Pacific Motorway, Eight Mile Plains to Daisy Hill Upgrade, to improve 8kms of the Pacific Motorway (M1) between the Gateway Motorway and Watland Street.
The Yatala South (Exit 41) interchange upgrade on the Pacific Motorway (M1) has resulted in significant enhancements to safety and traffic flow in the area.
The Exit 49 interchange upgrade will deliver significant improvements in safety and traffic flow efficiency by keeping traffic moving through the improved interchange and thereby reducing queuing.
Repairs are underway across southern Queensland after extensive and severe damage to the state-controlled road network was caused by multiple heavy rainfall and flooding events in 2022.
This planning project established a long-term vision to provide suitable active transport facilities between Tor and Boundary streets encourage more people to ride more often.
Planning is underway for another key link in Toowoomba's Principal Cycle Network.
The department has finalised planning on the Toowoomba North South Transport Corridor.
The Australian and Queensland governments are working together to deliver the Toowoomba to Brisbane Passenger Rail Strategic Business Case.
The Australian and Queensland governments are working together to deliver the Toowoomba to Gladstone Inland Rail Extension Business Case.
Detailed design commenced in October 2023 and is expected to be completed in June 2024.
The Warrego Highway East master plan project will determine the future requirements of the Warrego Highway transport corridor.
This project is part of a state-wide strategy to help improve bicycle riding facilities and networks in Warwick to increase active transport.
Last updated: 23 July 2024