The department is working on more than 920 projects to restore roads across Queensland damaged by floods and bushfires. The department is also reconnecting communities and supporting regional economic recovery after disaster events damaged the state-controlled road network in 2020, 2021, 2022, 2023 and 2024.
About the program.
- The Natural Disaster Program reconnects Queenslanders by repairing parts of the state-controlled road network damaged by natural disasters.
- The department restores damaged sites to their pre-disaster level of service.
- In the first 3 months after disaster events, the department undertakes emergency works such as clearing debris and filling potholes. This enables roads to be used safely while the department completes geotechnical and environmental investigations, surveys and detailed design for reconstruction works, where required.
- Reconstruction works are completed within 2 financial years after the financial year in which the disaster event occurred.
- Where possible, the program also supports the resilience of state roads to future disasters.
Current status
- Damage assessments and repairs are underway across Queensland after significant disaster events in 2023–24. Tropical Cyclone Jasper caused multiple landslips on range roads around Cairns, a major debris clean-up is ongoing following severe storms across southern Queensland and flooding associated with Tropical Cyclone Kirrily damaged roads in western Queensland.
- Repairs are ongoing after flooding across northern and central Queensland in early 2023.
- A substantial recovery program is underway, particularly across southern Queensland, after major disaster events caused extensive damage in 2021–22. The program is repairing significant state road damage across 41 local government areas, including numerous major landslips, widespread pavement damage and shoulder scouring and widespread scouring around culverts and bridges.
- Repairs are nearing completion in the Gold Coast hinterland following heavy rainfall and flooding in December 2020 and March 2021.
- Reconstruction works are underway on the Cunningham Highway where bushfires caused significant slope damage at Cunninghams Gap in late 2019. Due to the severe damage and complex site, repairs are being undertaken over an extended period.