The department is undertaking integrated planning for the Gateway Motorway and Bruce Highway Upgrades in north Brisbane and the Moreton Bay Region.

Each day, around 160,000 vehicles travel between the Moreton Bay Region and north Brisbane on the Gateway Motorway, Bruce Highway and Gympie Arterial Road.

Significant population growth is increasing travel demand through this road corridor, with current traffic levels expected to increase by around 50% by 2041.

These projects are part of an integrated approach to planning for the Gateway Motorway and Bruce Highway Upgrades that investigate:

Benefits

  • Improves safety
  • Increases capacity
  • Improves network efficiency
  • Reduces peak hour congestion
  • Better road access
  • Reduces travel time
  • Contributes to economy
  • Contributes to regional growth
  • Better active transport

Flythrough video

Video Transcript

00:00

Video starts - zoomed out map of north Brisbane area.

Green line depicts project extents - from south: starting at Gateway Motorway at Bracken Ridge, extending north to merge with the Bruce Highway, continuing north on the Bruce Highway through Dohles Rocks Road interchange and north until just south of Anzac Avenue.

  • Labels point to key areas of interest along the green line:
  • Project section: Gateway Motorway (Bracken Ridge to Pine River)
  • Key area: Gateway Motorway – Bracken Ridge curve
  • Project section: Bruce Highway (Gateway Motorway to Dohles Rocks Road)
  • Key area: Major upgrade at the Gateway Motorway/Bruce Highway/Gympie Arterial Road interchange
  • Key area: Dohles Rocks Road exit and entry ramps upgraded
  • Directional labels:
    • To Brisbane (down)
    • To Sunshine Coast (up)

00:34

Labels: Benefits (icons):

  • Increase capacity and reduce congestion
  • Improve safety
  • Improve freight efficiency
  • Better active transport

00:43  

Label: Upgrading one of Queensland’s busiest road corridors

Label: Traffic levels to increase by more than 50 per cent in 20 years on the Gateway Motorway and Bruce Highway

01:00

Zooms to start the ‘flythrough’ at the southern extent of the project

Gateway Motorway at Depot Road - facing northbound.

Moving northbound along Gateway Motorway starting at Depot Road Bracken Ridge, near the Deagon Deviation.

Labels: Gateway Motorway and Deagon Deviation

Label: Additional lanes in both directions (on the Gateway Motorway)

Label: 100km/hr speed limit

01:14

Gateway Motorway is lowered as it curves to the left, under the new Bracken Ridge Road overpass and reconfigured interchange.

Around the curve, the widened Gateway Motorway continues west towards the merge with Bruce Highway.

Label: Gateway Motorway is lowered

Label: Bracken Ridge Road over the motorway

Label: Bracken Ridge Road Exit ramp

Label: Bracken Ridge Road

Label: Upgraded Bracken Ridge Road Exit and Entry ramps

01:46

Upgraded Bracken Ridge Road entry and exit ramps shown joining Gateway Motorway, on left.

Tinchi Tamba Wetlands (on right of motorway)

Label: Fauna fencing along Tinchi Tamba Wetlands (on right of motorway corridor)

Label: New bridges over Bald Hills Creek.

Label: Potential fauna underpass (shown near Bald Hills Creek corridor)

02:02

Label: Wyampa Road

Upgraded Wyampa Road overpass bridge travels over the top of the Gateway Motorway lanes.

Northbound collector-distributor road exit lanes shown on the left of the motorway.

Southbound collector-distributor road lanes enter/merge with motorway on the right.

02:13

Top left of screen: orange line depicts future upgrades to the Gympie Arterial Road

Label: Future upgrades Gympie Arterial Road

02:14

Label: major interchange upgrade

02:17

Flythrough comes into the Gateway Motorway/Bruce Highway/Gympie Arterial interchange

Label: Gateway Motorway priority connection at 100km/hr.

Gateway Motorway merges with the Bruce Highway at ground level.

Northbound collector-distributor road traffic travels on flyover over the Gympie Arterial Road, arcs to the left and then joins/merges to run adjacent to the Bruce Highway, northbound.

Label: Potential fauna overpass

Label: To Gympie Arterial Road

Label: Bruce Highway

02:30

Southbound collector-distributor roads are depicted on the right of screen, with exiting traffic joining the Gateway Motorway, curving to the right.

Southbound collector-distributor traffic exiting to Gympie Arterial Road travels on a flyover over the Bruce Highway corridor to merge with the Gympie Arterial Road.

Label: Southbound collector-distributor

02:37

Flythrough travels north along the widened Bruce Highway, extending over the Pine River.

Northbound and southbound collector-distributor roads are shown on either side of the Bruce Highway (northbound on left, southbound on right of highway corridor).

Additional bridges are shown over Pine River on either side of Bruce Highway to accommodate the CD roads.

Label: Northbound collector-distributor

02:40

A green highlighted line is shown on the right-hand side of the new southbound collector-distributor road, depicting the new shared pathway for pedestrians and bike riders extending north, adjacent to the Bruce Highway road corridor.

Label: Shared path over the Pine River (right hand side-East)

02:41-6           

Label: Potential fauna underpass, on northern side of the Pine River. To assist east-west fauna movements under the Bruce Highway corridor.

02:58

Flythrough continues north, depicting widened Bruce Highway and additional northbound/southbound collector-distributor roads on either side of the Bruce Highway corridor.

Label: Bruce Highway to Sunshine Coast

03:13

Northbound collector-distributor road exits to the left of screen to Dohles Rocks Road.

Label: Collector-distributor exits to Dohles Rocks Road

03:13

Southbound collector-distributor road from Dohles Rocks Road enters on the right of the screen.

Label: Dohles Rocks Road entry to collector-distributor.

03:27

Flythrough slows to hover at the Bruce Highway - Dohles Rocks Road interchange.

Dohles Rocks Road runs east-west under the Bruce Highway corridor.

03:28

Flythrough stops moving - looking north:

Label identifies the start of the Bruce Highway (Dohles Rocks Road to Anzac Avenue) Stage 1 project.

On left:

  • Label: New extended entry ramp
  • Orange line: depicts new entry ramp extending north on Bruce Highway from Dohles Rocks Road.

On right:

  • Label: New extended exit ramp
  • Orange line: depicts new exit ramp extending south from Bruce Highway to meet Dohles Rocks Road.

03:35

  • Music stops. Branding slides. Australian Government logo and Queensland Government logos.

Video ends.

Community consultation

Have your say

Community consultation for 2023 has closed.

The department would like to thank the community for providing feedback on the recommended planning for Gateway Motorway (Bracken Ridge to Pine River) and Bruce Highway (Gateway Motorway to Dohles Rocks Road).

TMR will continue to engage the community and provide further opportunities for feedback when planning progresses to design and construction. For more information, visit the consultation page.

Previous consultation

The community and key stakeholders provided their feedback during community consultation from October to December 2022.

This feedback was considered to inform the development of the three business cases. 

A summary of the feedback is available to view.

Community impacts

The department recognises these upgrades will create changes in the local areas and we are committed to minimising these as much as possible as planning progresses.

Property

Property impacts are expected from the upgrades, and we are engaging with impacted property owners. 

Environmental management

There will be impacts on some surrounding wetlands and park areas. We are working to minimise these impacts with local environmental and community groups wherever possible.

Noise 

Planning is considering potential changes to road traffic noise. This will include identifying possible noise treatment such as noise barriers.

Gateway Motorway and Bruce Highway upgrades location map

Map depicting area of Gateway Motorway and Bruce Highway Upgrades area.  Starts from Gateway Motorway at Bracken Ridge and extends north through to the interchange with Bruce Highway and Gympie Arterial Road, crossing the Pine River and on the Bruce Highway through the Dohles Rocks Road interchange then extending north to Anzac Avenue interchange. The map shows the project area extending south from Bruce Highway onto Gympie Arterial Road through to Strathpine Road.

Map depicting area of Gateway Motorway and Bruce Highway Upgrades area. Starts from Gateway Motorway at Bracken Ridge and extends north through to the interchange with Bruce Highway and Gympie Arterial Road, crossing the Pine River and on the Bruce Highway through the Dohles Rocks Road interchange then extending north to Anzac Avenue interchange. The map shows the project area extending south from Bruce Highway onto Gympie Arterial Road through to Strathpine Road.

56 Projects in Gateway Motorway and Bruce Highway upgrades

No image supplied

Banyo level crossing precinct upgrade

We have investigated safety and congestion improvements for the Banyo level crossing precinct.

No image supplied

Bayside and Redlands Transport and Mobility Study

The Bayside and Redlands Transport and Mobility Study will investigate opportunities to enhance movement to, from and within the study area.

No image supplied

Beams Road (Carseldine and Fitzgibbon), upgrade rail level crossing

The Beams Road rail level crossing project will reduce congestion and address safety concerns. The current rail level crossing on Beams Road will be replaced with an overpass to separate road and rail.

No image supplied

Bicentennial Bikeway, Kurilpa Bridge to Victoria Bridge, design active transport upgrades

The department is designing an upgraded link for bicycle riders and pedestrians between Kurilpa Bridge and Victoria Bridge on the Bicentennial Bikeway.

Boundary Road Coopers Plains Rail Crossing map

Boundary Road (Coopers Plains), rail level crossing, funding commitment

A preferred option has been identified to reduce congestion and address safety concerns at Boundary Road, Coopers Plains rail level crossing.

No image supplied

Brisbane Metro – Woolloongabba Station

Planning is underway to deliver more benefits to our customers by integrating Brisbane Metro into the Woolloongabba precinct and connecting Brisbane's busway network with Cross River Rail.

Aerial view of road, trees, cars and houses

Bruce Highway (Brisbane - Gympie), Gateway Motorway to Dohles Rocks Road upgrade (Stage 1)

The Bruce Highway - Gateway Motorway to Dohles Rocks Road (Stage 1) project is part of integrated planning for the Gateway Motorway and Bruce Highway Upgrades in north Brisbane and the Moreton Bay Region.

No image supplied

Bruce Highway (Brisbane - Gympie), Gateway Motorway to Dohles Rocks Road upgrade (Stage 2), detailed design

The Bruce Highway - Gateway Motorway to Dohles Rocks Road (Stage 2) project is part of integrated planning for the Gateway Motorway and Bruce Highway Upgrades in north Brisbane and the Moreton Bay Region.

Artist’s impression of the extended north-facing ramps at Dohles Rocks Road interchange on the Bruce Highway, looking north.

Bruce Highway (Brisbane-Gympie), Dohles Rocks Road to Anzac Avenue upgrade (Stage 1)

The department is delivering staged upgrades to manage increasing traffic demands on this section of the Bruce Highway. Stage 1 includes extended north-facing ramps from Dohles Rocks Road to Anzac Avenue.

No image supplied

Bulimba Peninsula Transport and Congestion Study

The Bulimba Peninsula Transport and Congestion Study identified community priorities to improve transport options and outcomes for the Bulimba Peninsula.

No image supplied

Cannon Hill Shopping Centre bus facility, design bus station

The Cannon Hill Shopping Centre bus facility is proposed to be upgraded.

Centenary Bridge Jindalee artist impression Sept 2020

Centenary Bridge Upgrade

The Centenary Bridge Upgrade in Jindalee will increase capacity and improve safety on the Centenary Bridge by building a new 3-lane northbound bridge and rehabilitating the existing bridges to 3 lanes southbound including upgrades to active transport facilities.

No image supplied

Centenary Motorway (Yamanto – Ellen Grove) and Springfield Greenbank Arterial exit ramp, upgrade intersection

The department is working with Ipswich City Council to upgrade the Centenary Motorway exit ramp (Exit 32), and the Main Street and Springfield Greenbank Arterial Road intersection, to manage congestion and improve safety at the exit ramp.

Centenary Motorway project map - October 2023

Centenary Motorway planning, Australian Government funding commitment

The department is developing a masterplan for the Centenary Motorway corridor between Darra and Toowong to improve safety, travel-time and meet the increasing transport demands of the community.

No image supplied

Cleveland - Redland Bay Road, Anita Street to Giles Road, duplicate lanes

The department is upgrading Cleveland-Redland Bay Road, between Anita Street and Giles Road in Redland Bay.

No image supplied

Cleveland-Redland Bay Road upgrade

The department is undertaking a $110 million package of works to upgrade Cleveland-Redland Bay Road.

No image supplied

Cunningham Arterial Road (Ipswich Motorway) Rocklea to Darra, remaining sections, planning

The department is undertaking planning for the remaining sections of the Ipswich Motorway between Rocklea and Darra.

Thumbnail image of map showing location of upgrade section for the Cunningham Highway and Ipswich–Rosewood Road intersection in Amberley.

Cunningham Highway (Ipswich–Warwick) and Ipswich-Rosewood Road intersection, business case

Planning has started for an interim upgrade of the Cunningham Highway and Ipswich–Rosewood Road intersection in Amberley.

No image supplied

Cunningham Highway Upgrade

Planning is underway to upgrade the Cunningham Highway.

Eastern Transitway

Eastern Transitway (Stage 1), bus priority works

The Eastern Transitway will provide bus customers in Brisbane's east with a safer and more efficient public transport network. The project will deliver targeted bus priority measures to improve safety, reliability, and capacity along Old Cleveland Road from Coorparoo to Carindale.

Flood resilience works

The department is improving the flood immunity and resilience of the state-controlled road network at 27 priority sites.

Aerial view of roads, cars, trees and houses

Gateway Motorway, Bracken Ridge to Pine River upgrade

The Gateway Motorway (Bracken Ridge to Pine River) project is part of integrated planning for the Gateway Motorway and Bruce Highway Upgrades in north Brisbane and the Moreton Bay Region.

Thumbnail of map showing the proposed expansion of parking facilities at Gaythorne train station park 'n' ride

Gaythorne train station park 'n' ride, design and land acquisition

Detailed design has started for future expansion of parking facilities at Gaythorne station.

No image supplied

Gympie Arterial Road (Bald Hills), replace and improve noise barriers

The department is replacing a section of noise barriers on the western side of Gympie Arterial Road, north of Strathpine Road in Bald Hills.

No image supplied

Ipswich City Transport and Mobility Study

Ipswich is a rapidly growing and dynamic local government area. New neighbourhoods are emerging and existing communities continue to expand and mature. People's travel behaviours and expectations around a wider range of travel choices and modes are changing.

Ipswich to Springfield Public Transport Corridor Study

We have started the next stage of planning for a future Ipswich to Springfield public transport corridor. 

No image supplied

Ipswich-Cunningham Highway Connection Road (Brisbane Road), Chermside Road and Glebe Road (East Ipswich Fiveways), improve intersection

The department undertook community consultation in early 2021 on a proposed improvement for the Ipswich-Cunningham Highway Connection Road (Brisbane Road), Chermside Road and Glebe Road (East Ipswich Fiveways) intersection in East Ipswich. The proposed upgrade included changing Glebe Road into a cul-de-sac to improve safety and traffic flow.

No image supplied

Kenmore Bypass Planning Study

A study has been undertaken to investigate a bypass at Fig Tree Pocket using the existing preserved corridor.

Artist impression of how the upgraded Kuraby train station will look. The image shows the the new Kuraby entrance from street view with a train pulled into the station.

Kuraby train station upgrade

Kuraby station is being upgraded to improve accessibility, safety and customer experience for the community. 

No image supplied

Lindum Station Precinct Upgrades

We are working with all levels of government to improve safety and accessibility at the Lindum Station and level crossing.

No image supplied

Linkfield Road Overpass upgrade

The department has been investigating options to reduce traffic congestion and improve safety and freight access for the Linkfield Road Overpass in Bald Hills.

Manly Boat Harbour Aerial

Manly Boat Harbour

The Manly Boat Harbour is an integral part of the bayside’s social, cultural and economic landscape. We are currently undertaking a master planning process to help guide future activities at the boat harbour.

Project location runs along Moggill Road from the intersection of Rafting Ground Road and Moggill Roadd to the Centenary Motorway

Moggill Sub - Arterial Road, Centenary Motorway to Rafting Ground Reserve, active transport planning

Planning is underway to improve active transport infrastructure and safety along Moggill Road.

Moggill Sub-Arterial Road and Brookfield Road (Kenmore) intersection upgrade map

Moggill Sub-Arterial Road and Brookfield Road (Kenmore) intersection upgrade (Kenmore roundabout)

In 2021, an upgrade was proposed for the Kenmore roundabout at the intersection of Moggill Road and Brookfield Road in Kenmore. The upgrade proposed removing the roundabout and signalising the intersection, and also included provision for active transport users.

Map showing roads subject to planning including, Mount Cotton Road (Duncan Road to Double Jump Road), Redland Bay Road (Tingalpa Creek to Cleveland-Redland Bay Road), and Redland Sub-Arterial Road (Mount Gravatt-Capalaba Road to Tingalpa Creek).

Mount Cotton Road, Duncan Road to Double Jump Road, planning study

The department is undertaking a planning study for Mount Cotton Road, Redland Bay Road and Redland Sub-Arterial Road.

No image supplied

Mount Lindesay Arterial Road Beaudesert Road Kameruka Street upgrade intersection

The department is undertaking planning to progressively upgrade the Beaudesert Road corridor, from the Logan Motorway towards Compton Road.

Northern Transitway final design map

Northern Transitway

The department is delivering targeted bus priority from Kedron to Chermside, improving the safety and capacity of this important link in Brisbane's northern public transport network.

Northgate station park 'n' ride business case

The department has completed planning which investigated expansion of parking facilities at Northgate station in response to high demand for parking in the local area.

Map showing roads subject to planning including, Mount Cotton Road (Duncan Road to Double Jump Road), Redland Bay Road (Tingalpa Creek to Cleveland-Redland Bay Road), and Redland Sub-Arterial Road (Mount Gravatt-Capalaba Road to Tingalpa Creek).

Redland Bay Road, Taylor Road to Cleveland Redland Bay Road, planning study

The department is undertaking planning for Mount Cotton Road, Redland Bay Road and the Redland Sub-Arterial Road.

Mount Cotton Road-Redland Bay Road location map

Redland Sub-Arterial Road, Mount Gravatt Capalaba Road to Tingalpa Creek, widening, business case

The department is undertaking planning for Mount Cotton Road, Redland Bay Road and the Redland Sub-Arterial Road.

No image supplied

Road Asset Management Contract and Responsive Maintenance Contract—Metropolitan

In April 2019, Fulton Hogan and RoadTek were awarded 5-year contracts to undertake responsive maintenance and road asset management services across the Metropolitan Region.

No image supplied

Salisbury to Beaudesert Rail Business Case

We are planning for a proposed passenger rail line between Salisbury and Beaudesert.

No image supplied

Salisbury train station, construct park 'n' ride

Stage 1 of the Salisbury train station park ‘n’ ride is now complete.

Map of Samford Road interection improvements

Samford Sub-Arterial Road (Samford Road) and Glen Holm Street, upgrade intersection and Samford Sub-Arterial Road (Samford Road) and Osborne Road intersection planning (known as the Samford Road intersection improvements)

Initial community consultation was undertaken on proposed safety and traffic improvement works at key intersections along Samford Road, at Glen Holm Street and Osborne Road.

No image supplied

South Brisbane Transport and Mobility Study

We conducted a multi-modal study of the ongoing and increasing transport pressures relating to road, active transport and public transport modes in Brisbane’s inner south.

No image supplied

South East Queensland Rail Stabling Program

We are working in partnership with Queensland Rail to develop a number of new purpose-built, modern train stabling facilities across the rail network critical to accommodate new trains delivered by the New Generation Rollingstock (NGR) project.

Landslip on Gold Coast - Springbrook Road

Southern Queensland 2022 flood reconstruction works

Repairs are underway across southern Queensland after extensive and severe damage to the state-controlled road network was caused by multiple heavy rainfall and flooding events in 2022.

No image supplied

Stafford Road and South Pine Road Intersection Upgrade planning study

The Stafford Road and South Pine Road Intersection Upgrade planning study delivered a 2-staged concept plan to improve traffic flow and increase capacity. The plan includes safety improvements at Sizer and McIlwraith streets, as well as pedestrian and bike riding upgrades in the area.

No image supplied

Toowoomba to Brisbane Passenger Rail Strategic Business Case

The Australian and Queensland governments are working together to deliver the Toowoomba to Brisbane Passenger Rail Strategic Business Case.

Veloway 1: Lower River Terrace Velobridge

The Veloway 1 (V1) is a dedicated bikeway designed to connect people riding bikes between Lower River Terrace, South Brisbane and Eight Mile Plains, adjacent to the Pacific Motorway.

Veloway 1 in use artist impression

Veloway 1: Pacific Motorway

The Veloway 1 is a dedicated cycleway running between Lower River Terrace, South Brisbane and Underwood. The 20km cycleway provides a safe and efficient route for bike riders.

Warrego Highway Mount Crosby upgrade project area aerial image

Warrego Highway (Ipswich - Toowoomba) and Mount Crosby Road interchange, detailed design

The department has completed planning to identify a preferred option for the upgrade of Warrego Highway – Mount Crosby Road interchange.

Bremer River Bridge project location map

Warrego Highway (Ipswich - Toowoomba), Bremer River Bridge, strengthening

The Bremer River Bridge project includes critical rehabilitation and strengthening repair works, including bridge re-decking, to extend the life of the existing westbound bridge structure.

No image supplied

Western Brisbane Transport Network Strategy